Track record

Projects

Seven completed packages across Jeddah, Muzdalifa, Taif, Tabuk and Riyadh — bridges, underpasses, water retention and intersections — and four more under way.

7 completed4 in progress
Bridge at Abdul Aziz Street, Jeddah
01 / 07JeddahBridge

Bridge at Abdul Aziz Street

An elevated carriageway on one of Jeddah’s principal arterial routes, delivered in sixteen months.

Project duration
16 months
Configuration
1 direction, 2 traffic lanes
Project detail
Intersection of Prince Majid St., Jeddah
02 / 07JeddahIntersection

Intersection of Prince Majid St.

A grade-separated intersection carrying three lanes in each direction, built over eighteen months.

Project duration
18 months
Configuration
2 directions, 3 traffic lanes each
Project detail
Firefighting Water Tank, Muzdalifa
03 / 07MuzdalifaWater infrastructure

Firefighting Water Tank

A 20,000 m³ firefighting reservoir cut into the hillside at Muzdalifa, roofed with pre-cast tiles and beams on 150 internal columns — completed in five months.

Contract value
23,500,000 SAR
Completion date
2007
Project duration
5 months
Tank capacity
20,000 m³
Volume of concrete
15,000 m³
Excavation
200,000 m³
Project detail
Water Tank, Taif
04 / 07TaifWater infrastructure

Water Tank

A circular reservoir at Taif delivered complete with its civil and electromechanical works.

Scope
Civil and electromechanical works
Project detail
Bridge & Underpass at Pr. Majed Road, Jeddah
05 / 07JeddahBridge & underpass

Bridge & Underpass at Pr. Majed Road

A 700 m bridge on pre-cast post-tensioned U-girders over an 800 m top-down underpass, completed February 2018.

Contract value
82,800,000 SAR
Completion date
February 2018
Role
Subcontractor
Volume of concrete
35,000 m³
Excavation
30,000 m³
Steel
6,000 tons
Project detail
Omar Bin Khatab Bridge, Tabuk
06 / 07TabukBridge

Omar Bin Khatab Bridge

A 750 m bridge carrying three lanes in each direction, built over a twenty-four month programme.

Contract value
52,000,000 SAR
Project duration
24 months
Length
750 m
Configuration
2 directions, 3 traffic lanes each
Volume of concrete
12,000 m³
Excavation
50,000 m³
Steel
3,000 tons
Project detail
Bridge over Wadi Barqa, Riyadh
07 / 07RiyadhBridge

Bridge over Wadi Barqa

A wadi crossing carrying four lanes in each direction, founded in rock and delivered over twenty-four months.

Project duration
24 months
Configuration
2 directions, 4 lanes each
Project detail

On site now

Ongoing
projects

An example of excellence in executing projects.

Our on-going projects are an example of our style of managing projects. A glance at the mechanism and sequential order of the project reflects our ways and means of handling projects.

Neom City

Construction of a civil 30-storey building

Building
Neom City

Pipeline project

Pipeline
Neom City

800 metres of road construction, 2 lanes of traffic each direction

Roads
Dammam

Construction of a civil 8-storey building

Building
Pipeline sections laid out at Neom City
Structural works under way
Bulk earthworks and rock excavation